PROJECT SCHEDULE + UPDATES
Q1 2025
PROJECT START
This project will start in Q1 of 2025
Q1 2025
PROJECT PERIMETER
Shutdown of one Eastbound lane of Morganton Road and the Southbound lane of Highland Avenue
Q2 2025
DEMOLITION
Full Demo is scheduled for March
Q3 2025
FOUNDATION
Foundations are scheduled to begin second quarter
Q3 2025
MASONRY
Masonry started Q3 & Q4 of 2025, and Q1 of 2026
Q1 2026
MEP
Mechanical + Electrical, + Plumbing Underground
Q1+Q2 2026
STEEL ERECTION
Steel erection Q1 & Q2 of 2026
Q2 2026
Topping Out
Topping Out ceremony
Q1 2026
CONCRETE POURS
Concrete pours that will require early morning/late evening disturbances in Q1 + Q2, more to come
Q2 2026
DRY-IN + EXTERIOR
Dry-in and exterior finishes Q2 of 2026
Q2 2026
INTERIOR
Interior finishes Q2 & Q3 of 2026
Q3 2026
PROJECT COMPLETION
This project will be completed around Q3 2026.