PROJECT SCHEDULE + UPDATES
Q1 2025
PROJECT START
This project will start in Q1 of 2025
Q1 2025
PROJECT PERIMETER
Shutdown of one Eastbound lane of Morganton Road and the Southbound lane of Highland Avenue
Q2 2025
DEMOLITION
Full Demo is scheduled for March
Q3 2025
FOUNDATION
Foundations are scheduled to begin second quarter
Q3 2025
MASONRY
Masonry to begin late second quarter
Q4 2025
STEEL ERECTION
Steel erection will begin third quarter
Q4 2025
CONCRETE POURS
4 concrete pours that will require early morning/late evening disturbances in Q3 + Q4, more to come
Q1 2026
DRY-IN + EXTERIOR
Dry-in and exterior finishes late fourth quarter
Q2 2026
INTERIOR
Interior finishes early first quarter 26’
Q3 2026
PROJECT COMPLETION
This project will be completed around Q2 2026.