CAPE FEAR REGIONAL THEATRE

Project Update 8.11.25

Project Update 8.11.25

Project Update 8.11.25 Samet Managed and coordinated daily site activities Schedule and develop agendas for upcoming meetings Reviewed current ASI’s/shop drawings Misc. interactions with the public Site maintenance Superior Concrete of NC Pre-tying Rebar...
August Update

August Update

CAPE FEAR / AUGUST UPDATE About Majority of Civil and Building Demo is complete. The building pad is read to go! Footings and foundations to start beginning of August. After footings, we will work through under ground rough-ins on our way to going vertical Q4 2025...
CFRT Capital Expansion- September Update

CFRT Capital Expansion- September Update

CFRT Capital Expansion – September Update Credit Link: https://www.cfrt.org/capital-campaign/act-2-expand-elevate/ About This September, Footloose audiences were the first to see our architect’s white model rendering, along with new images of the rooftop event...
CFRT Capital Expansion Introduction

CFRT Capital Expansion Introduction

CFRT Capital Expansion Introduction Credit Link: https://www.cfrt.org/capital-campaign/act-2-expand-elevate/ About In January 2021, we officially opened our newly renovated auditorium with our LAUNCH PARTY! Donors, patrons, and special guests were the first ones to...
CFRT Capital Expansion- May Update

CFRT Capital Expansion- May Update

CFRT Capital Expansion – May Update Credit Link: https://www.cfrt.org/capital-campaign/act-2-expand-elevate/ About Our May update for Sister Act audiences featured our BRAND NEW, final building design, PLUS info about our 2024/2025 season:...